Detention and Retention Ponds

A pond is a hole with rules. It has a bottom elevation, a side slope, an outlet and a place for the extra water to go when the storm is bigger than the design. Dig it too shallow and it does not hold the volume. Dig it too deep and it holds water the plan never meant to keep. Cut the outlet a few inches off and the basin drains too fast or not at all.

Detention ponds slow runoff from paved and roofed areas and release it at a controlled rate. Retention ponds hold the water until it soaks in or evaporates. On large industrial and commercial sites, one or the other is almost always required, and it is usually the first piece of earthwork that has to be right. The rest of the site drains to it.

We build ponds as engineered structures: surveyed, compacted, shaped and stabilized. They look like landscape features once the grass comes in. They work like dams.

Big acreage, big runoff

The scale of local industrial land makes ponds a real design item. Casper Logistics Hub is Magnet Site 2 of Foreign Trade Zone 157 at 6 Mile Road and Commerce Street, listed at 984 acres, and Foreign Trade Zone 157 also operates a 492 acre Magnet Site at the airport. A site of that size, once paved and roofed, sheds enormous volumes of water in a storm and needs basins sized to it.

The ponds on such sites tend to be large, shallow and shared between lots. That gives developers a choice between building a regional basin up front or building separate basins lot by lot. We price both and explain what each does to the phasing. A regional pond front-loads the earthwork but frees later pads from building their own. On big parcels such as the logistics hub, that choice often shapes the whole development.

What pond construction includes

Pond work begins with stripping topsoil and unsuitable material, then excavating to the design bottom. Cut material is hauled to fill areas on the same site wherever possible, which can pay for the pond by balancing the earthwork. Where the basin sits above grade, we build embankments in compacted lifts with a key into stable soil.

The outlet is the most important structure. It is usually a concrete outlet box with an orifice and a weir, connected to a discharge pipe. The emergency spillway, a wide, armored notch in the embankment, handles flows above design. We also install inlet aprons, forebays that trap sediment, riprap at energy points and maintenance access for equipment. A related package covers pond and basin excavation for owners who need only the dirt work, and our storm lines feed straight into the basin through storm drain installation.

Design rules and permits

Pond design follows the local drainage criteria and the project's stormwater plan. Casper's climate summary lists severe weathering, and that applies to a basin as much as to a building: freeze-thaw cracks outlet structures and slopes erode through cycles of wetting and drying. The outlet concrete is air-entrained and well cured, and the slopes are seeded, matted or armored as the plan requires.

Stormwater permitting covers the construction period, and a separate permanent plan covers operation. Large sites typically need an engineered drainage report and an approved erosion plan before the first load of dirt moves. We bring in the trade team for mass grading to carve the basin first, because the pond often doubles as a sediment trap during construction. Cleaning it out and finishing it to final grade comes at the end of the project.

What sets the price of a pond

Volume drives it. Every cubic yard has to be dug, hauled, placed and compacted or wasted. The next driver is what happens to the spoil. If the site needs fill, a pond pays for itself. If the site is balanced or in surplus, the extra dirt has to go somewhere, and hauling is expensive in a region with long distances.

Soil type matters. Clean granular soils drain quickly, which suits detention but makes a retention pond leak. A retention pond over permeable ground may need a clay liner or a geomembrane. Groundwater, rock and the outlet structure add cost. We give owners a unit price per cubic yard for excavation and haul and a lump sum for the outlet works, and we explain the swing items. Industrial and manufacturing owners often ask for a spill containment feature at the outlet, which adds a gate valve and a small structure.

Shape, compact, stabilize

Layout is by survey. We stake the toe and the top, check the bottom elevation with a laser and cut to a tolerance tight enough that the pond holds its design volume. Side slopes follow the plan, often 3 horizontal to 1 vertical or flatter so maintenance equipment can reach them. Embankment fill goes in thin lifts with moisture control and density tests.

The outlet goes in before the basin fills with water. We place the concrete, cure it and backfill around it in even lifts so the pipe does not break. Once the basin is shaped, we stabilize it with seed, mulch or erosion mat. A bare pond slope loses inches to the first storm. In dry country, seeding timing matters, so we plan it with the weather and not around the calendar.

Which buildings need big ponds

The largest basins serve buildings with the most roof and pavement. A logistics fulfillment center may carry hundreds of thousands of square feet of roof and a ring of trailer parking. A truck terminal and cross-dock has long paved aprons that shed water fast.

Airport-area land is its own case. The airport covers 5,150 acres, and projects on and near the airport campus must also consider wildlife and bird attractants. Standing water draws birds, so designers often favor dry detention basins that drain within a set time. We build to those drawings and tell owners what a wet pond would do to the operation.

Deep water, steep slopes and heavy iron

Pond construction uses large equipment on unstable edges. We keep haul roads separate from working areas, use spotters at the embankment and make sure operators know the slope limits. Wet bottoms get pumped before heavy equipment goes in. Open basins are fenced or signed when the site is not staffed, and water that collects is a drowning risk for children and animals.

Outlet structures and pipes are confined spaces during construction. We restrict entry, ventilate and monitor. Heavy rain during construction can fill a basin quickly and wash out a fresh embankment, so we watch the forecast and keep temporary pumping and diversion ready.

Send the grading and drainage plan

Share the grading plan, drainage report and soils data. We will quantify the cut and fill, price the outlet works and tell you whether the pond can pay for itself.

Questions Owners Ask

What is the difference between a detention pond and a retention pond?

A detention pond holds stormwater and releases it slowly through an outlet, and it is normally dry between storms. A retention pond holds a permanent pool or lets water infiltrate or evaporate. The drainage plan sets which one is required, and the soil often decides if it is practical.

Can the pond be built early to help during construction?

Yes, and it often should be. A rough-cut basin serves as a sediment trap for the whole site. We finish the outlet and shape the slopes at the end, after the pavement and landscaping are in. That saves a second pass and keeps silt out of the downstream system.

How do you handle all the dirt a pond produces?

We plan the earthwork so cut from the pond becomes fill for pads and berms on the same site. When the quantities do not balance, we haul the surplus to a designated stockpile or disposal area. A balanced plan reduces trucking and cost, so we look at the whole grading plan, not the pond alone.

Do ponds freeze or crack?

The concrete outlet structures can, if the concrete is not air-entrained and cured well. Earth slopes can slough in freeze-thaw. We specify and place durable concrete, grade slopes to the design, and stabilize them with vegetation or armor.

How much maintenance does a pond need?

Expect to inspect after major storms, clean out the forebay when sediment builds up, mow or manage vegetation and clear the outlet of debris. We build in access for equipment and leave a maintenance record. A well-built pond needs little, but an ignored one fills with silt and stops working.

Related

Ready to talk about your project?

Request a Project Review

Ready to talk about your project?

Send the plans to Concrete Contractors of Casper info@concretecontractorscasper.com

Back to Concrete Services

Call307-344-4067