Fulfillment Center Floors and Site Work

Pick modules and conveyor lines care about floor flatness more than almost any other trade does. A mezzanine on columns that settle, a sorter that runs out of level or a narrow-aisle truck that wanders on a rolling floor all trace back to the slab. A fulfillment center in Casper is a concrete job first, with a building built around the floor.

The metro offers one unusual advantage for this type of building: an airport with scheduled and cargo flights, a Foreign Trade Zone and a business park, sitting next to Interstate 25. Casper-Natrona County International Airport covers 5,150 acres and has a 10,165 foot runway. A cargo carrier flies into it daily. For a fulfillment operator that wants parcels to move by road and air, the combination is hard to find in a metro this size.

We build the floors, the mezzanine slabs, the employee lot and the truck court. The notes below explain what we plan for and where the dollars go.

Airport ground and the Interstate

Foreign Trade Zone 157 is operated by the airport and includes a Magnet Site of 492 acres at 8500 Airport Parkway, with a boundary covering nearly all of Natrona County. The business park next to the field already houses more than 35 businesses, from manufacturing to aviation. A fulfillment operator that sits in the airport area can use the zone for some goods and the cargo flights for others.

On the north side of town, Westwinds Road, exit 194, opened in October 2018 as an Interstate interchange. The north Casper corridor has access to the highway without crossing the center of the city. Another diamond interchange, exit 189, carries US 20 and 26 west toward the airport. Building near either gives trucks an easy first and last mile.

Developers, operators and the retail connection

Fulfillment buildings are usually developed on spec by commercial developers or built for a specific operator. In either case the building is leased or sold on specifications: clear height, column spacing, dock count and floor flatness numbers. Those numbers translate into our work as thickness, joint layout, finishing method and tolerances.

Downstream, the buyers are often retailers. The retail shopping centers at the other end of the supply chain receive those same pallets. For fulfillment operators who ship direct to consumers, employee parking and shift-change traffic matter as much as truck flow, and we design the lot for both.

Flat floors, mezzanines and parking

Floors are poured with laser screeds in long strips, with finish timing set to the day's weather. Where the specification requires, we use super flat floor slabs methods: tight subgrade tolerances, controlled mix and a finishing crew sized to the pour. Joints are sawn early and filled later, after the slab shrinks, and the layout keeps joints away from the racking and conveyor footprint where possible.

Mezzanines add elevated concrete or steel with a concrete topping. For a concrete topping on metal deck, elevated slabs and decks are placed with a pump, screeded to elevation and cured under a controlled cover. Equipment such as sorters and tilt-tray lines may need thickened pads or embedded plates; we form them to the vendor drawings and place them in the same pour sequence as the slab.

Treating the floor as the last step of the dirt work

Floor flatness starts well below the slab. We test the subgrade, correct soft spots, compact in thin lifts and trim the final grade with a laser-controlled blade. A base course is then trimmed to tolerance. A well-built base is the reason a floor measures flat on day 28 as well as day one. The same discipline applies to a plain warehouse shell, but a fulfillment floor leaves less room for error.

We also schedule around the racking contractor. Racking is bolted down into the slab, so the slab must reach strength first. Cold-weather curing, joint filling and the final cleaning all take time. We put the racking contractor's start date on the same calendar as the pour, so no one is waiting.

What shifts the floor and site price

The first is the flatness spec. A tighter spec requires better subgrade work, more finishing labor and sometimes a restriction on pour size, and all of those cost money. The second is slab thickness and reinforcement, which depend on the rack loads and the vehicle fleet. Third is the mezzanine and the equipment pads, which are often priced per square foot of elevated slab.

The employee lot and the truck court are the other half of the site. A fulfillment center with high headcount needs more stalls than a warehouse. Winter placement adds cost, and so do extra mobilizations if the pour is split. We separate those items in the estimate. For tenants with a post-tensioned approach, we also price post-tensioned slabs where the engineer wants fewer joints in the floor.

Lease dates, peak season and the weather

Fulfillment operators think in terms of peak season: the building must be live before the volume arrives. That puts pressure on the schedule during the very months when Casper weather is hardest. We work backward from the date the racking has to be up, and we tell the owner when the slab has to be poured to meet it.

If the floor cannot be poured before cold weather, the building should be enclosed and heated first, which is a cost the owner should know early. If the building must open before the truck court is done, we pour an interim gravel surface and return for the concrete in spring. Neither is ideal, but both beat a rushed pour in a cold snap.

Send the flatness spec and the racking plan

Send us the floor flatness requirement, the racking plan and the site. We will give you a pour plan, a schedule that matches your peak season and a price split by floor, mezzanine and yard.

Questions Owners Ask

How flat does a fulfillment floor need to be?

It depends on the equipment. Narrow-aisle trucks, automated vehicles and high racks all have flatness requirements in the specification. We build to the number in the drawings and measure the floor after the pour. If a section fails, we tell the engineer and discuss grinding or other remedies.

Can mezzanine slabs be poured in winter?

Yes, if the building is enclosed and heated and the pour is protected. We cover the deck, keep the temperature above the minimum required, and monitor the concrete until it gains strength. Heated enclosures and blankets are additional costs, which we list separately.

Does a Foreign Trade Zone site change the concrete work?

Not the concrete, but it can change the site. A secure yard, gates, fencing and lighting may be needed, and those affect pavement and utility layout. We ask about zone status at the start, so the site plan includes what the operator needs.

How much parking should we plan for employees?

The count comes from shift size and overlap. A fulfillment center can have hundreds of workers arriving at once, so we plan stalls and aisles for peak shift change. We also separate employee traffic from trucks wherever the parcel allows.

When is the right time to start site work?

As early as the permit allows. The city permit is good for 180 days, so we coordinate the start of site work with the building permit. Underground work and pad grading in summer give the floor a better chance of finishing before freeze-up.

Ready to talk about your project?

Request a Project Review

Ready to talk about your project?

Send the plans to Concrete Contractors of Casper info@concretecontractorscasper.com

Back to Building Types

Call307-344-4067